Implemetation Phase

Flowchart outlining Phase 2 implementation for Highway 6 / Hanlon Expressway Midblock Interchange (GWP 3059-20-00), including design-build milestones, environmental assessments, and reporting steps.

The image is a flowchart titled “Implementation of Phase 2: Highway 6 / Hanlon Expressway Midblock Interchange (GWP 3059-20-00).” It visually represents the sequence of tasks and milestones involved in executing Phase 2 of the project.

Flowchart Elements (Top to Bottom):
Advertisement of the Request for Proposal – occurred in June 2021.
Award of the Project to the Design-Build Contractor – anticipated early 2022.
Phase 2 Design-Build Project begins.
Continuation of Detailed Design and Class Environmental Assessment by the Design-Build Contractor.
Finalize Design and Construction Staging/Sequencing using frameworks from the Design-Build Ready Phase.
Confirm Environmental Impacts and Mitigation Measures for construction; obtain or finalize all necessary permits and approvals.
Issue Design and Construction Report(s) for public and agency review.
Annual Reporting on Ministry of Environment, Conservation and Parks’ Conditions of Approval.
Orientation and Relationships:
The flowchart is arranged vertically, showing a clear progression from planning to execution and reporting.
Each step is connected logically, emphasizing dependencies and regulatory compliance.
The design uses boxes and arrows to guide the reader through the process.